A KAMAZ truck of the garbage operator contractor Citymatic-Volgograd cut power lines at the largest waste sorting plant in the Svetloyarsky district of the Volgograd region, as a result of which the operation of the entire complex was paralyzed, the company said. local news agency Vysota 102. on May 5
The accident occurred the day before, the driver of the contractor’s special transport did not lower the handler’s arm and damaged the power line, the waste processing plant was completely de-energized. Poles were demolished, plant structures and electrical panels were damaged, and the operation of the complex was completely stopped.
According to representatives of the contractor company Citymatic-Volgograd, due to the reduction in the hours of operation of the waste sorting company, the intensity of the truckers’ work has increased in recent days in order to avoid overflowing the sites with waste. solid. . Due to the busy work schedule of the drivers, an emergency occurred: the human factor worked, according to the company.
Citymatic-Volgograd LLC stated that they are ready to provide assistance and do not absolve themselves of responsibility, and are also waiting for the restoration of the waste sorting complex’s working hours in accordance with the contract.
Currently, specialists are restoring power supply at the enterprise, the exact time has not yet been announced.
Source: Rossa Primavera

I am Michael Melvin, an experienced news writer with a passion for uncovering stories and bringing them to the public. I have been working in the news industry for over five years now, and my work has been published on multiple websites. As an author at 24 News Reporters, I cover world section of current events stories that are both informative and captivating to read.